Second opinion on €287,400 renovation budget for a 95 m² serviced apartment in Rome

travelsAndGrove

Property investor
Established
The visible work is reasonably well defined, but the condition behind the finishes is not. I have a preliminary allowance of €287,400 for a 95 m², five-bedroom serviced apartment in Rome, covering the kitchen, bathrooms, floors, decoration, electrical assessment and some energy-efficiency work. There is no planned extension.

My main concerns are concealed plumbing, damp and any structural work revealed after opening up, rather than the choice of finishes. If targeted inspections show that the services and wet areas are sound, I could keep a smaller reserve and defer cosmetic items. If access or moisture problems appear, I would want a much larger contingency before appointing the contractor. What should be inspected now, and which exclusions should every bidder be required to price?
 
For this scope I would initially reserve around 15% rather than assume the quoted total is firm. Ask the contractor to list exclusions explicitly: rewiring versus testing only, replacement of concealed pipework, opening and reinstating walls or floors, moisture treatment, waste removal, permits and temporary protection. Also get lead times for anything that must be installed before surfaces are closed.
 
I’m not sure a percentage is meaningful yet. Is the apartment vacant during the work, and does the budget distinguish visible bathroom fittings from the drainage and supply routes behind them? Five bedrooms in 95 m² could make access and sequencing unusually tight. I’d want targeted opening-up in the wet areas and an electrical assessment before deciding whether 15% is enough.
 
One more point: “no structural extension” does not necessarily mean no structural uncertainty. Confirm whether any walls will be altered, chased heavily for services or loaded with new equipment. Then build a room-by-room sequence showing investigations, permits if required, first-fix electrical and plumbing, moisture drying, finishes and commissioning. That should expose clashes before the contractor prices them as variations.
 
Fair challenge on the percentage. I’d treat 15% as a starting reserve, not the answer. The practical next step is to split the €287,400 into firm scope, provisional items and optional cosmetics. Resolve electrical capacity, plumbing routes and moisture first; confirm permit timing and long-lead materials next. Flooring and paint can remain later phases, which matches Maria’s priorities and protects the budget if concealed work expands.
 