Renovation budget for a 50 m² mixed-use building in Singapore — what am I missing?

KeenInk

Property investor
Established
I keep going back and forth between carrying a large contingency now and asking contractors to narrow every uncertain item before setting one. The working budget is S$319,500 for renovating a 50 m² mixed-use building in Singapore.

The planned work covers the kitchen, bathrooms, floors, painting, electrical checks and moderate improvements to energy use. There is no proposed structural extension. Finishes are fairly easy to specify; opening walls or floors, gaining access to plumbing and coordinating the order of work are less predictable.

What would you require in the survey and contractor quotations before reducing the contingency? I’m particularly interested in separately priced exclusions, responsibility for making good after access work, signs of moisture, the boundary of the electrical work, approval timing and long-lead items.
 
For an early budget, I’d tentatively hold 15–20% until the hidden conditions are better defined, then reduce it only when access and scope are confirmed. Ask contractors to state exclusions explicitly: hacking and disposal, opening and reinstating walls or floors, waterproofing repairs, temporary services, protection of occupied areas, testing and making good. Also clarify whether any wall changes could turn the supposedly non-structural job into something more involved.
 
The missing fact is whether the residential and commercial parts remain occupied or operating during the works. If so, sequencing may cost more than the physical work because electrical or plumbing shutdowns, noisy work and access have to be phased. Do the kitchen and bathrooms share accessible service routes, and is there any visible staining or persistent damp smell?
 
I wouldn’t rely on one percentage alone. Build a small risk schedule beside the S$319,500: concealed plumbing, moisture remediation, electrical replacement beyond checks, permit delay and long-lead materials. Give each a provisional allowance or note how it will be priced if discovered.

Before appointing anyone, request a room-by-room scope, programme showing shutdowns and inspections, and a written list of client-supplied items and contractor exclusions. That will expose more than comparing headline totals.
 