Renovation budget for a 45 m² Osaka townhouse — am I overthinking it?

knitsAndHarbor

Property investor
Established
The finishes are not what worry me; it is what might be uncovered once this 45 m² Osaka townhouse is opened up. I have a working budget of ¥59,640,000 for renewing the kitchen and bathrooms, replacing floor finishes, redecorating, checking the electrics and improving energy performance. There is no added floor area in the plan.

At this early stage, how much would you keep outside the quoted work for surprises? I would also like to know which inspections best expose structural or moisture problems, and how contractors should state assumptions about demolition, access and remedial work. Material lead times matter too because one delayed item could disrupt the sequence in such a small space. I am happy to reduce the specification if that protects the cash reserve.
 
At a genuinely preliminary stage, I’d separate a 15–20% contingency from the construction price rather than letting it disappear into finish upgrades. The percentage can come down once access and existing conditions are understood.

Ask each contractor what they have assumed about structural repairs, rewiring beyond failed points, pipe replacement, moisture damage, demolition and disposal. Also ask what event turns an allowance into an extra charge.
 
Before choosing a percentage, do you have drawings showing plumbing routes and electrical distribution, and can the property be opened up before the final quote? Plumbing access could drive both cost and sequence in only 45 m². I’d also clarify whether the ¥59,640,000 includes design fees, approvals, temporary works and tax, or is purely the building contract.
 
I disagree slightly with starting from a contingency percentage. A large reserve does not fix an undefined scope; it can simply make a vague quotation feel safer. I’d spend effort first on targeted opening-up where practical: around wet areas, concealed pipe runs and any visibly suspect wall or floor junctions. Moisture findings may affect flooring, bathrooms and insulation in one go.
 
One more sequencing point: ask who is responsible for identifying any permits or approvals, when that decision is made, and whether the programme includes the relevant timing. Then map long-lead materials against demolition, electrical work, plumbing and closing the walls. A beautiful schedule that assumes every item arrives on demand is not much protection.
 
Contractor exclusions deserve their own comparison sheet. Look for testing, making good after electrical or plumbing access, moisture treatment, structural repairs discovered during demolition, waste removal and final finishes around replaced components.

I would also ask for separate prices for “must do,” “should do while open,” and optional design work. That gives you somewhere sensible to simplify without cutting work needed to close the building back up.
 
This has helped me reframe it. I’m going to stop treating ¥59,640,000 as one all-purpose ceiling and break it into defined scope, allowances, exclusions and a separately controlled contingency. Before fixing the percentage, I’ll request plumbing-access information, targeted opening-up, clearer electrical assumptions, moisture checks, approval responsibility and a lead-time-based sequence. Optional finishes will be the first items reduced if the essential scope firms up above plan.
 