Renovation budget and contingency for a 170 m² Berlin townhouse

sailsAndWall

Homeowner
Established
The proposed scope is being treated as non-structural, and that is the part I hesitate to rely on in an older Berlin townhouse. I’m testing a €72,040 budget for 170 m², covering the kitchen, bathrooms, floors, decorating, electrical review and some energy-efficiency work. There is no extension in the plan.

Once walls or floors are opened, moisture, wiring or structural defects could upset both cost and sequence. How much would you hold outside the main budget, and what should a surveyor or contractor investigate before pricing? I also want to identify exclusions and material lead times rather than spend time choosing finishes too early.
 
With that much uncertainty, I would initially keep 15–20% outside the working budget rather than allocating it to upgrades. Ask each contractor to list exclusions explicitly: rewiring versus testing only, making good after electrical work, pipe replacement, moisture treatment, waste removal and any structural repairs uncovered during demolition. A price that simply says “bathroom renovation” is too vague to test.
 
How many bathrooms are included, and will the house be occupied during the work? Those two facts could materially affect both cost and sequencing. I’d also establish whether plumbing can be reached from existing service voids or requires floors and walls to be opened. For the electrical scope, ask what happens if the checks reveal that partial replacement is impractical.
 
I’m not convinced a contingency percentage alone solves this. If €72,040 is based on broad allowances, the underlying scope may be incomplete rather than merely uncertain. Before settling on 15–20%, get room-by-room quantities and separate prices for opening up, remedial work and reinstatement. A limited investigative phase could be more valuable than collecting several apparently precise whole-project quotes.
 
Sequencing matters especially around moisture and services. Investigate damp areas before fitting floors or painting, then settle plumbing and electrical routes before closing walls. Ask who is responsible for testing moisture levels, protecting completed work and repairing surfaces opened by another trade. Also confirm which kitchen, bathroom and energy-upgrade materials must be ordered early, because substitutions can disrupt both price and programme.
 
One caveat: don’t let “no extension” become shorthand for “no structural issue.” Existing walls, floors or supports may still need attention once exposed. I’d ask the surveyor to identify where targeted opening-up would answer the most expensive questions, then have contractors price those findings rather than guess. Keep permit timing, if any part of the final scope requires approval, separate from material lead times in the schedule so the cause of delay is visible.
 