Reconciling two renovation quotes for a 105 m² Seoul warehouse

bakesAndView

Developer
Established
The two quotes cannot really be compared yet. My specific concern is that each contractor has interpreted the hidden work differently.

The project is a 105 m² warehouse in Seoul with a preliminary budget of ₩284,800,000. The intended work covers new kitchen and bathroom areas, finishes, electrical review and some energy improvements, without adding an extension. Before setting the contingency, I plan to put both bidders against one room-by-room scope showing inclusions, exclusions and sequencing.

What investigations should accompany that document? I’m particularly concerned about access to drains, damp in the roof or walls, and work that could become structural even though the footprint is unchanged. A concrete example would be whether a new ventilation opening needs support that neither quote currently includes.
 
Before choosing a contingency, make both contractors reprice against one written scope and exclusions list. “Electrical checks” could mean inspection only for one bidder and replacement work for the other. The same ambiguity applies to plumbing connections and energy upgrades.

For planning, I’d carry 15% and test whether the project still works at 20%, but keep that allowance outside the contractor’s visible spending pot.
 
What was the warehouse previously used for, and are the existing kitchen and bathroom locations close to usable drains? Moving waste lines can affect floors, levels and sequencing even without an extension.

I’d also investigate roof and wall moisture, floor condition, electrical capacity, and any openings needed for ventilation. “No extension” doesn’t necessarily mean no structural work if equipment or new openings alter loads.
 
One more practical step: ask each bidder to separate confirmed work, provisional allowances and exclusions. Then request unit prices for the likely discoveries—floor repair, cable replacement, additional plumbing runs and moisture treatment. A low total containing many provisional items is not really cheaper; it has simply postponed the price difference.
 
I agree with the comparison grid, but I wouldn’t automatically commission every intrusive survey before appointing anyone. Access may be limited, and opening finishes without a coordinated plan can create extra repair work.

A short pre-construction phase may be better: targeted openings at drain routes and damp areas, verification of the electrical scope, then a revised fixed scope. The contingency should cover genuine discoveries, not items that could have been clarified first.
 
Also ask both contractors for a sequence tied to decisions and material orders, not just a completion date. Bathrooms, kitchen equipment, ventilation and energy-upgrade components may need confirmation before floors and ceilings close up. Separately, have someone familiar with the Seoul jurisdiction identify any required approvals and their timing; don’t let an assumed permit date sit invisibly inside the programme.
 
I’d turn the next meeting into a reconciliation exercise rather than a negotiation over the two totals. Use one room-by-room scope, mark who supplies each item, define disposal and protection, and record testing and handover requirements. Then list assumptions about drains, incoming power, moisture and substrate condition.

After that, split the reserve into design development, hidden conditions and client changes. That makes it much easier to see whether 15–20% is prudent or whether the current ₩284,800,000 figure is simply missing defined work.
 