Contingency and sequencing for an older 175 m² Dubai coastal renovation

daily_porch

Property investor
Established
AED 469,600 looks workable as a starting figure, but concealed moisture is the concern that could overturn it. The property is an older 175 m² coastal home, and the intended renovation includes the main interiors, wet areas, service checks and some energy improvements rather than an extension.

Before treating the budget as fixed, I want to understand the likely structural repairs, access needed for pipes and wiring, and the order in which walls, floors and bathrooms should be opened. Material lead times could also leave completed work exposed or force substitutions. If inspections can establish that the structure and concealed services are sound, would a normal percentage reserve be enough? If they cannot, would you price separate allowances for moisture, electrical and access work instead? What exclusions should every contractor be required to identify?
 
For that combination of age, coastal exposure and several wet areas, I would keep the contingency separate rather than burying it in trade allowances. Something around 15–20% seems more comfortable until intrusive inspections clarify the walls, floors and services. Ask each contractor to list exclusions explicitly, especially waterproofing repairs, corroded wiring or pipework, making good after access, permit-related changes and disposal.
 
Does the AED 469,600 already include design fees, permit costs, temporary accommodation and long-lead material storage, or is it construction only? That distinction changes whether Maria’s contingency is genuinely available for hidden conditions.

I’d also ask where plumbing isolation points and access panels are located. A bathroom price can look complete while excluding the work needed to reach or replace concealed lines.
 
I’m not convinced a percentage alone solves this. If moisture or electrical defects are widespread, even 20% may just provide false comfort. Before appointing the main contractor, investigate the highest-risk areas and request separate prices for defined scenarios: local repair, full bathroom waterproofing replacement, partial rewiring and inaccessible plumbing. Then reserve contingency for what still cannot reasonably be inspected.
 
Agreed with nbakker that investigation should come before relying on the percentage. I’d sequence it as survey and moisture assessment, limited opening-up where permitted, service testing, then a revised scope and contractor comparison.

Also ask bidders to provide a programme showing permit assumptions, material lead times and which rooms must be opened simultaneously. Compare exclusions line by line, not just totals. Keep the contingency controlled by the owner and require written pricing before it is used.
 