Setting contingency for a £205,800 renovation of older student housing in Birmingham

DirectCairn

Homeowner
Established
I have allowed £205,800 for renovating 970 sq ft of older student housing in Birmingham, and I have already ruled out an extension. What remains unclear is how much hidden work sits behind the kitchen, bathrooms and existing services.

Plumbing access worries me most because opening a boxed-in waste run could affect several rooms and the order of the whole job. I also need to establish whether approvals or permit timing could delay the start. Before setting the contingency, what investigations would you commission, and which contractor exclusions would you insist on seeing in writing?
 
Before choosing a contingency percentage, clarify what the £205,800 includes. Does it cover VAT, professional fees, approvals, finance costs and any period when the property cannot be occupied? Also ask each contractor for a written exclusions list. A broad allowance means little if rewiring, damaged subfloors, asbestos investigation or making good after opening walls sits outside the price.
 
I would not assume that an older building automatically needs a huge contingency. The better approach is to spend more of the pre-contract period reducing uncertainty: moisture readings, targeted opening-up where acceptable, tracing water and waste routes, and confirming the condition and capacity of the electrical installation.

Ask who pays when access reveals extra work, and whether the price includes closing walls and redecorating afterward. Those boundaries cause arguments more often than the visible materials.
 
There is still a sequencing risk even with good surveys. Energy upgrades can affect ventilation and moisture behaviour, while bathroom and kitchen layouts depend on practical plumbing routes. Get the proposed order of work written into the programme and identify long-lead materials before strip-out. I would also separate genuine unknown-condition contingency from allowances for items that simply have not been selected yet.
 
One caveat: targeted opening-up is useful only if the owner permits it and the areas chosen are representative. I would ask contractors to price the same scope, state assumptions about wall and floor construction, and give separate figures for likely electrical, plumbing and moisture discoveries. Confirm approval timing before fixing a start date, then model the finance cost of delay as well as the building contingency.
 