Sanity-checking a R$2,130,000 renovation budget for a 70 m² coastal home

openTheRiver

Developer
R$2,130,000 is the figure I need to test, because the contractor quotes do not appear to cover the same scope.

This is for a 70 m² coastal home in São Paulo. The proposed work covers the kitchen and bathrooms, new floors and paint, electrical assessment and some energy improvements. I am not planning an extension, but concealed moisture or building defects could still turn it into structural work.

What contingency would be sensible once the quotes are made comparable? I also need a practical list of questions for the surveyor and contractors about waterproofing, plumbing access, wiring, permits, sequencing and long-lead materials. My next step is to have every bidder identify exclusions and responsibility for anything uncovered during demolition.
 
I would provisionally carry 15%, rising toward 20% if walls and wet areas cannot be inspected before signing. But first make the exclusions comparable. Ask each contractor who pays for damaged concealed plumbing, corroded wiring, failed waterproofing, substrate repairs and any structural remediation discovered after demolition. “Electrical checks” is especially vague: have them state exactly what testing, replacement and certification are included.
 
I would not rely on even a 20% contingency until the R$2,130,000 is broken down line by line. A percentage can conceal an undefined scope.

Is this São Paulo city or a coastal municipality in São Paulo state? That may affect access, permit timing and contractor logistics. I would request a demolition-first sequence, moisture inspection, plumbing-access plan, materials schedule with lead times, and written responsibility for permits and debris removal. Keep hidden-condition money separate from finish upgrades so it is not spent early.
 