Renovation contingency for a 220 m² warehouse in Seoul

lookTheRiver

Homeowner
Established
I have reviewed the visible scope, but the building services remain the weak point in the estimate. The working budget is ₩114,100,000 for a 220 m² warehouse in Seoul, including new kitchen and bathroom areas, floors, decoration, an electrical review and limited energy improvements. No extension is intended.

I do not want to choose finishes before knowing whether the electrical capacity, drainage and moisture conditions are suitable. If the existing routes can be reused, a conventional reserve may be enough; if floors or walls must be opened, the programme and contingency both change. Which inspections should come first, and what should contractors confirm about exclusions, material lead times and permit-related delays?
 
With the electrical and plumbing condition still unclear, I would provisionally ring-fence around 20% rather than spend the whole ₩114,100,000 on the visible scope. Ask bidders to state assumptions for electrical capacity, drainage routes, slab penetrations, moisture remediation, access and making good. A low bid is not comparable if those items are simply excluded.
 
One missing fact: what will the warehouse be used for after renovation, and are the kitchen and bathrooms replacing existing facilities or being installed in new locations? That changes the questions considerably. Existing service routes could keep the work straightforward; new wet areas may introduce drainage, waterproofing and sequencing issues.
 
I would not solve an incomplete scope merely by increasing the contingency percentage. First pay for enough investigation to distinguish genuine unknowns from work that should be priced now: electrical inspection, plumbing and drainage access, moisture mapping, and a structural look wherever loads or openings might change. Then keep contingency for what remains unknowable rather than for vague contractor allowances.
 
Agree with Liam on investigation, but the programme also needs attention. Moisture work must precede flooring and paint, and concealed electrical or plumbing changes should be finished before surfaces are closed. Give every bidder the same requested sequence and ask which materials have long lead times, what alternatives they allow, and exactly who carries delay risk when approvals or deliveries slip.
 
That is fair—I wasn’t suggesting 20% as a substitute for defining the work. I’d keep it outside the contractor’s base price while the inspections are happening. Also ask whether the quote assumes the existing structure can accept any kitchen equipment, suspended services or energy-upgrade components. “No extension” does not necessarily mean there will be no structural questions.
 
Moisture deserves its own line rather than being buried under flooring. Ask where water enters, whether the test was done in suitably revealing conditions, and whether the proposed price covers only drying and coating or also fixing the cause. Otherwise a contractor can complete attractive finishes while excluding the problem underneath them.
 
Permit timing may be the schedule wildcard, particularly if the intended use, occupancy arrangements or building services are changing. I would ask a Seoul-based designer or permit specialist which parts of this exact scope need approval and what information must be submitted. Get that clarified before committing to delivery dates or ordering items that depend on the final layout.
 
For the next round, issue a simple room-by-room scope plus an exclusions sheet. Have bidders separately price demolition, disposal, temporary protection, electrical work, plumbing, moisture treatment, making good and finishes. Add columns for allowance, fixed price and excluded. That makes gaps visible and lets you release work in sequence instead of discovering halfway through that two trades each assumed the other would handle access.
 
The most useful next step is probably to reconcile the ₩114,100,000 against that exclusions sheet before choosing a contingency. Confirm whether it includes design and permit costs, testing, temporary works, waste removal, final connections and reinstatement after inspections. Once Joana clarifies the future use and whether the wet areas are moving, the remaining risk allowance can be based on specific unknowns rather than one blanket percentage.
 