Renovation contingency for a 170 m² Tokyo townhouse

walksAndKey

Property investor
Established
I want a renovation programme firm enough to price before committing, but too much of the work is still hidden. The working budget is ¥41,190,000 for a 170 m² Tokyo townhouse. It includes new kitchen and bathroom work, replacement finishes, painting, investigation of the electrics and some energy improvements; there is no planned extension.

Finish choices are not my main worry. I’m more concerned about moisture, concealed plumbing, the exact electrical scope and the order in which investigations and construction should happen. What contingency would you retain until those items are opened up or surveyed?

I also want bidders to identify exclusions, responsibility for making good after inspections, material lead times and any permit-related delay. Is there a particular survey report or scope schedule that would make their quotations genuinely comparable?
 
Without good drawings or any opening-up work, I would keep an owner-held contingency around 15–20%, rather than letting the full amount become a vague contractor allowance. The lower end may be reasonable if the layout and wet areas stay put; the upper end gives more room if services are concealed and poorly documented. Ask for exclusions in writing, especially making good after investigation.
 
The missing facts are the building’s age, construction type, whether kitchen or bathroom fixtures are moving, and whether it will be occupied during the work. Those answers could change both sequencing and contingency. I’d also ask whether the electrical figure means inspection only, replacement of identified faults, or broader upgrades. “Electrical checks” is too open-ended for comparing bids.
 
Fatima’s point about moving wet areas is important. Give each contractor the same room-by-room scope and ask them to identify assumptions about pipe routes, drainage access, wall and floor opening, temporary protection, disposal, and reinstatement. Also ask what happens commercially when an inspection reveals extra work: agreed rates, a fresh quotation, or use of an allowance. That process matters almost as much as the percentage.
 
I’m not convinced one contingency percentage is the best way to think about this. Separate known-but-unpriced items from genuinely hidden conditions. Material selections and quantities should be priced or carried as explicit allowances; concealed moisture, inaccessible plumbing and unexpected structural repairs belong in the owner reserve. Otherwise normal scope gaps consume the contingency before demolition starts.
 
One sequencing point: obtain lead-time information before fixing the demolition date. Kitchens, bathroom components, flooring and energy-upgrade items can affect when areas are opened and closed. Ask for a programme showing investigation, ordering, approvals if required, strip-out, service work, inspections, waterproofing, finishes and commissioning—not merely a start and completion date.
 
For moisture and plumbing, request targeted investigation where bathrooms, kitchens, external walls and service routes create the greatest uncertainty. The useful question is not just “is there moisture?” but how far the contractor can inspect without destructive work, what remains unverified, and who repairs test openings. Permit requirements can depend on the actual work, so have the designer or contractor list which parts may require approvals and include that timing explicitly.
 
Before choosing a contractor, I’d issue the same scope, drawings and assumptions list to at least two bidders, then compare exclusions rather than totals alone. Require each to return a proposed sequence, procurement list, unresolved questions and responsibility matrix for design decisions. Keep the ¥41,190,000 base budget separate from the contingency and maintain a decision deadline for every owner-selected item; late choices can create costs that have nothing to do with hidden conditions.
 