Renovation contingency for a 1,610 sq ft coastal home in Chicago

CarefulFinch

Developer
The ₩—rather, $361,400—budget is substantial for 1,610 sq ft, but concealed defects are my main concern. This is a Chicago home described as coastal, and the planned work covers the kitchen, bathrooms, floors, decoration, electrical inspection and some energy improvements without an extension.

Cosmetic selections can be changed or deferred; opening walls and discovering moisture, damaged wiring or difficult plumbing access is another matter. If surveys show the structure and services are sound, I could carry a moderate reserve and control the finishes. If those areas remain uncertain, I would rather increase the reserve or narrow the scope. What investigations and contractor exclusions should be settled before I commit to the budget?
 
For an older property with several rooms being opened up, I’d tentatively reserve around 15% rather than treat 10% as automatically sufficient. Ask bidders to list exclusions and allowances separately, including wall repairs after electrical work, plumbing access, disposal, temporary protection and permit-related costs. Also confirm whether “electrical checks” means inspection only or includes money for corrective work.
 
Before choosing a percentage, does “coastal home” describe the design style or actual exposure near the lake? That changes how seriously I’d investigate moisture around windows, roof edges, basement or crawl spaces.

I’d also ask whether the kitchen and bathrooms are moving. Keeping fixtures in place is very different from rerouting plumbing through concealed floors and walls.
 
Coastal mainly describes the style, although moisture investigation is still sensible. The kitchen layout is broadly staying put, and I’m not planning major bathroom relocations. I’ll tighten the brief around electrical corrective work, wall making-good and plumbing access; those are currently too vague. The 15% suggestion feels prudent, but I’d prefer to reduce unknowns before simply adding a larger reserve.
 
If the unknown items are grouped into one percentage, the reserve could disappear before the real problems are reached. The missing detail for me is how much of the $361,400 is already supported by fixed quotations and how much is still an allowance.

For example, priced cabinets carry a different risk from wiring behind unopened walls. I would separate firm purchases, defined labour, provisional amounts and concealed-condition work, then weight the reserve toward the latter two. That would show whether 15% reflects evidence in this thread or merely compensates for an unfinished scope.
 
If responsibility for opening and repairing walls is left vague, two contractors may both exclude it and the owner pays twice. I would turn the current brief into a room-by-room schedule showing who exposes plumbing or wiring, who reinstates the surface, and how moisture or damaged material triggers approval for extra work.

Then stage the decision. Price accessible work first and photograph the existing services so every bidder sees the same evidence; hold permit-dependent work and long-lead orders until their sequence is confirmed. That reduces uncertainty without pretending every risk can be fixed in advance.
 