A vague exclusion can turn a workable budget into a sequencing problem once work has started. I am reviewing a preliminary allowance of ₹7,622,000 for renovating a 75 m² Bengaluru studio, and the contractor quotes do not appear to cover the same scope.
The project includes a kitchen, bathrooms, flooring, painting, electrical inspection and some energy improvements. No extension is intended, but I am less worried about finish choices than concealed moisture, remedial electrical work, access restrictions and materials arriving late.
What reserve would be reasonable at this stage, and which unknown would you investigate first? I would also like to know what wording to request on electrical replacement, moisture testing, opening-up and reinstatement, delivery lead times, debris removal and any building or permit approvals. A common written scope may be the only way to compare the quotes properly.
The project includes a kitchen, bathrooms, flooring, painting, electrical inspection and some energy improvements. No extension is intended, but I am less worried about finish choices than concealed moisture, remedial electrical work, access restrictions and materials arriving late.
What reserve would be reasonable at this stage, and which unknown would you investigate first? I would also like to know what wording to request on electrical replacement, moisture testing, opening-up and reinstatement, delivery lead times, debris removal and any building or permit approvals. A common written scope may be the only way to compare the quotes properly.