Renovation budget for a 75 m² studio in Bengaluru

studyTheRoom

Homeowner
Established
A vague exclusion can turn a workable budget into a sequencing problem once work has started. I am reviewing a preliminary allowance of ₹7,622,000 for renovating a 75 m² Bengaluru studio, and the contractor quotes do not appear to cover the same scope.

The project includes a kitchen, bathrooms, flooring, painting, electrical inspection and some energy improvements. No extension is intended, but I am less worried about finish choices than concealed moisture, remedial electrical work, access restrictions and materials arriving late.

What reserve would be reasonable at this stage, and which unknown would you investigate first? I would also like to know what wording to request on electrical replacement, moisture testing, opening-up and reinstatement, delivery lead times, debris removal and any building or permit approvals. A common written scope may be the only way to compare the quotes properly.
 
I would initially reserve around 15% and only reduce it after opening-up risks are clearer. Ask each contractor to price the same written scope and list exclusions beside every trade. The biggest questions are whether electrical “checks” include replacement work, how concealed plumbing will be accessed, who repairs finishes after that access, and whether moisture testing is included. Also confirm debris removal, protection of common areas and material storage.
 
Is this in an occupied apartment building, and will any walls or wet-area layouts change? “No extension” does not necessarily mean no structural or approval questions. Building access hours, lift use and permission for noisy work could affect sequencing.

I would also avoid treating the whole 15% as one pot. Keep separate allowances for hidden moisture/plumbing, electrical remedial work and schedule-related costs, otherwise an early upgrade can consume money needed for genuine defects.
 
Good distinction. I would ask for a room-by-room sequence before agreeing the contingency: investigation and moisture checks first, then any approvals, demolition, plumbing/electrical work, waterproofing, flooring and finishes. Long-lead kitchen or bathroom items should be identified before demolition begins.

The contractor should also state what happens if concealed damage is found: written variation, supporting cost breakdown and approval before proceeding. That will not remove surprises, but it prevents exclusions from becoming an open-ended second budget.
 