Renovation budget for a 65 m² condo in Dubai?

daily_porch

Property investor
Established
I have set out an initial AED 1,075,000 allowance for a 65 m² Dubai condo, but I have not established how much existing-condition risk sits outside that figure. The intended work includes the kitchen and bathrooms, new floors and paint, checks to the electrics and some energy improvements. There is no planned extension, although service routes or altered walls could still complicate the job.

The main decision is whether the scope is defined well enough to appoint a contractor or whether more investigation should come first. Which documents or site checks would confirm plumbing access, moisture around wet areas and any structural implications? I would also like the quotes to show who carries the cost of opening and making good, approvals, delays and long-lead materials before I settle on a contingency.
 
I’d provisionally hold 15–20% until the intrusive uncertainties are reduced, rather than burying contingency inside each trade allowance. Ask who pays for opening and reinstating walls, inaccessible plumbing, failed waterproofing, electrical upgrades beyond testing, building access restrictions and permit delays. Also request a room-by-room scope with explicit exclusions and lead times. “No structural extension” does not necessarily mean no structural risk if any walls, floors or service routes are altered.
 
I wouldn’t choose the percentage before separating design choices from existing-condition risk. Is AED 1,075,000 the contractor works only, or does it also include design, approvals, temporary accommodation, appliances and loose furniture? For the survey, prioritise moisture readings around both bathrooms and the kitchen, confirmation of plumbing access, and inspection of the electrical panel and circuits. Then sequence approvals and long-lead items before demolition; otherwise a generous contingency still won’t prevent delay.
 
Back
Top