Renovation budget for a 245 m² detached home in Seoul

bikesAndEcho

Homeowner
Established
The work needs a reliable sequence before finishes are ordered. Hidden pipework, moisture or permit delays could otherwise undo the budget.

I am testing ₩433,800,000 for renovating a 245 m² detached home in Seoul. The current scope covers the kitchen, bathrooms, flooring, painting, electrical assessment and moderate energy improvements, without a structural extension. What level of contingency would be sensible at this stage? I also want to know which surveys or contractor documents would clarify plumbing access, concealed damp, electrical remedial work and possible structural repairs. Should permit or approval requirements be confirmed before tendering, and how should bidders show allowances and exclusions for conditions that cannot yet be inspected?
 
I would keep the contingency unallocated until opening-up work is complete. Before finishes are ordered, investigate moisture-prone areas, confirm how bathroom and kitchen pipework can be accessed, and establish whether “electrical checks” includes only testing or also remedial work. Ask every bidder for a written exclusions list and separate allowances for concealed-condition repairs. That will make the ₩433,800,000 figure much easier to test.
 
Is the house occupied during the work, and do you know its age or renovation history? Those details could change the sequence substantially. I’d also ask whether any energy upgrades require walls or ceilings to be opened, because doing them after paint and flooring would create avoidable rework. A room-by-room scope may miss these dependencies; a systems-based schedule for plumbing, electrical, moisture treatment and finishes could be clearer.
 
I agree on defining electrical scope, but I would not postpone every material decision until opening-up. Long-lead items can disrupt the whole programme. Identify critical materials early, while making orders conditional where dimensions depend on exposed conditions. Also ask the contractor who carries delay risk for permits, approvals and late materials, and whether disposal, temporary protection, testing, making good and final cleaning are included. Hidden work matters, but vague exclusions can consume contingency just as quickly.
 