Renovation budget for a 230 m² Rotterdam duplex—what am I missing?

HonestHorizon

Architect
Established
If the estimate is too optimistic, the renovation could stop with the duplex half finished. I have €248,900 set aside for a 230 m², three-bedroom property in Rotterdam, covering new kitchen and bathrooms, floors, decoration, electrical testing and some energy-efficiency work. I am not planning an extension.

Before fixing the design, I want to identify the expensive unknowns. Which surveys would best expose moisture, concealed damage and difficult plumbing routes? I would also like contractors to spell out exclusions, responsibility for opening and restoring walls or floors, and whether permit timing could disrupt the order of work. If moving the kitchen or bathrooms changes the risk substantially, I can keep them near the existing services.
 
I wouldn’t apply one contingency figure to the whole €248,900 yet. First separate firm quotations, provisional allowances and completely untested work. The last category needs the most room.

Ask every contractor to list exclusions explicitly: opening and closing walls or floors, waste removal, making good after electrical and plumbing work, moisture damage, access equipment and temporary protection. Also confirm who coordinates trades. A cheap line item can become expensive when nobody has included the work around it.
 
Are you changing the kitchen or bathroom positions? That is the missing fact I’d want before commenting on the budget. Keeping services close to their existing locations is very different from routing new plumbing through a duplex where floor and ceiling access may be limited.
 
I partly disagree with waiting for every unknown to be resolved before setting contingency: some uncertainty will remain even after surveys. Reserve a protected amount now, then adjust it as opening-up work and quotations improve the picture.

I’d ask for moisture readings around wet rooms and external walls, an electrical scope that distinguishes testing from replacement, and confirmation that apparently non-structural layout changes do not affect load-bearing elements. Permit requirements and timing should be confirmed locally before ordering anything tied to the final layout.
 
Sequence the investigation before the finishes: moisture and structural questions first, then plumbing routes and electrical needs, followed by final kitchen and bathroom plans. Ask bidders to price the same written scope and identify material lead times, assumptions and exclusions beside each item. Keep design simplifications ready—such as retaining service locations—but don’t count the contingency as available for upgrades.
 