€59,900 feels tight for renovating 215 m², and my main concern is how much necessary work is missing from the quotes. This is a coastal home in Paris, with changes planned to the kitchen and washrooms, new floor finishes and decoration, plus electrical assessment and some energy improvements. I am not adding an extension.
Each contractor has left out different items, so the totals are not directly comparable. For example, one may include new plumbing but not the opening-up and reinstatement needed to reach it. Which investigations should come first, and how large a reserve would be sensible before access, moisture and the electrical condition are understood? I also need to know whether permissions, sequencing or material lead times could delay the programme. I am more willing to reduce the finish specification than leave hidden work unfunded.
Each contractor has left out different items, so the totals are not directly comparable. For example, one may include new plumbing but not the opening-up and reinstatement needed to reach it. Which investigations should come first, and how large a reserve would be sensible before access, moisture and the electrical condition are understood? I also need to know whether permissions, sequencing or material lead times could delay the programme. I am more willing to reduce the finish specification than leave hidden work unfunded.