A fixed contingency percentage would be simple, but I suspect the accessible evidence should determine the reserve here. I am testing a €336,500 renovation budget for a 165 m² studio in Madrid, covering kitchen and bathroom work, new floors, redecoration, electrical assessment and moderate energy improvements. The plan does not include an extension.
Before settling on the contingency, what should the surveyor and bidders verify about pipe access, moisture, the true electrical scope and earlier alterations? I am particularly concerned that opening walls or floors could reveal structural work even though no additional space is planned.
Before settling on the contingency, what should the surveyor and bidders verify about pipe access, moisture, the true electrical scope and earlier alterations? I am particularly concerned that opening walls or floors could reveal structural work even though no additional space is planned.