Renovation budget for a 165 m² studio in Madrid?

celine.young

Property investor
A fixed contingency percentage would be simple, but I suspect the accessible evidence should determine the reserve here. I am testing a €336,500 renovation budget for a 165 m² studio in Madrid, covering kitchen and bathroom work, new floors, redecoration, electrical assessment and moderate energy improvements. The plan does not include an extension.

Before settling on the contingency, what should the surveyor and bidders verify about pipe access, moisture, the true electrical scope and earlier alterations? I am particularly concerned that opening walls or floors could reveal structural work even though no additional space is planned.
 
With that many concealed elements, I would initially keep about 15% outside the working budget rather than letting it disappear into allowances. Ask every bidder for a written exclusions list, especially for rewiring beyond checks, inaccessible pipework, moisture remediation and any work uncovered after demolition. “No extension” does not necessarily mean no structural intervention if previous alterations are discovered.
 
Does the €336,500 include taxes, design and permit costs, appliances and temporary protection, or is it construction only? That changes how comfortable the contingency looks. I’d also want to know whether there are reliable existing drawings and whether ceilings, service risers and the areas below wet rooms can actually be inspected before pricing.
 
That distinction matters. I’d avoid one vague contingency covering everything: separate known allowances from genuinely unknown conditions. Kitchen equipment or tile selection can be priced later; hidden drains and undocumented electrical work cannot. Also ask contractors to identify long-lead materials now and state the last decision date for each, otherwise contingency gets consumed by rushed substitutions and resequencing.
 
I disagree slightly with choosing a percentage first. Spend effort reducing uncertainty before deciding the reserve: moisture readings, an electrical inspection, drain investigation where access permits, and limited opening-up in agreed locations. If plumbing is completely inaccessible, no contractor can give a firm number honestly. After that work, 15% may be cautious—or insufficient—depending on what appears.
 
Permit timing belongs in the sequence as well. Confirm the required route for this exact scope in Madrid before fixing demolition and trade dates; it can vary with the proposed work and the building. Then map dependencies: investigation, design decisions, approvals, strip-out, hidden-condition assessment, first-fix services, inspections where applicable, close-up, finishes. Require a change procedure with cost and time effects agreed before extra work starts.
 
The total alone is hard to judge without an elemental breakdown. I’d compare bids in the same table: included quantities, provisional amounts, exclusions, access assumptions, lead times and programme. Keep the contingency controlled by the owner rather than folded into the contractor’s price, and only release it against documented changes. The biggest warning sign would be a low bid that simply says electrical, plumbing or moisture repairs are “as required.”
 