Renovation budget for a 115 m² new-build flat in Dubai (2 bed)

AdaHope

Homeowner
Established
AED 532,000 is the preliminary figure I am testing for a 115 m² new-build flat in Dubai. Two contractors have returned very different prices, which makes me suspect they are not allowing for the same work.

The renovation includes a kitchen, bathrooms, new floors, painting, electrical work and modest energy improvements, with no extension. I plan to have both firms complete one itemised schedule showing materials, labour, approvals, protection, disposal and making good. The electrical section also needs to distinguish testing from moving sockets, lights or appliance feeds.

Before setting the contingency, what else should be fixed in writing? I am particularly concerned about material lead times, waterproofing, concealed services and exclusions that later become variations, rather than upgrading the finishes.
 
I would first make both contractors price the same itemised schedule. Ask each to separate supply, installation, approvals, protection, waste removal and making good. A headline difference often comes from one quote including those items and the other treating them as variations.

For early budgeting, I’d keep roughly 10–15% uncommitted, with more caution if bathroom waterproofing or concealed services remain uncertain.
 
Does “electrical checks” mean testing the existing installation, or moving sockets, lighting points and appliance feeds? Those are very different scopes. The same applies to the kitchen: keeping plumbing in place is not comparable with moving the sink or adding new connections. I’d get those boundaries written down before deciding whether the contingency is adequate.
 
I’d be wary of treating new-build as meaning no hidden conditions. Before finishes are removed, you may not know how easily the plumbing can be accessed or whether floor levels will work across different materials. Ask who pays for opening-up work, moisture findings, levelling and reinstatement. Those four items could explain a large part of the quote gap.
 
I disagree slightly with putting a percentage on it this early. AED 532,000 may contain generous allowances in one trade and almost nothing in another, so 15% on top could still miss the real exposure. Build a short risk allowance beside each uncertain item instead: bathrooms, floor preparation, electrical changes, access and material lead times.
 
Sequencing deserves its own conversation with both contractors. Ask for the order of demolition, service alterations, wet-area work, flooring, joinery, painting and final electrical fit-off. Then ask which materials must be selected before work begins. A low quote can become expensive if the programme assumes every tile, fitting and kitchen component is available exactly when needed.
 
That trade-by-trade approach is sensible, but I’d still retain a general reserve because not every problem fits a known category. The useful comparison would be: identical base scope, named allowances for unresolved selections, specific risk sums, then a smaller overall contingency. Otherwise it is easy to spend the entire reserve through upgrades before concealed work is opened.
 
Also clarify what “no structural work” means to each bidder. Even without an extension, proposed wall alterations, slab penetrations or heavy fixed items may trigger questions they have excluded. Ask them to mark every assumed penetration and service route on a drawing. If one contractor has allowed for difficult routing and the other has assumed clear access, the pricing difference becomes much less mysterious.
 
Permit and building-management timing could affect the programme even if it does not change the physical scope. I’d ask who submits what, which fees are included, what working-hour or access assumptions sit behind the schedule, and whether delays change supervision or mobilisation charges. The exact requirements can vary by building, so written confirmation from the relevant management side matters.
 
One more practical comparison: issue a list of exclusions and require both contractors to respond line by line. Include moisture testing, waterproofing repairs, plumbing access panels, floor levelling, electrical remedial work, temporary protection, debris removal, final cleaning and return visits. Silence should not be treated as inclusion. The cheapest-looking quote is often simply the least explicit.
 
This has helped narrow the problem. I’m going back to both contractors with one itemised schedule and drawings showing service changes and penetrations. I’ll separate unresolved bathroom, flooring, electrical and access risks from a smaller general contingency, rather than applying one percentage blindly.

I’ll also ask for a written sequence, material decision dates, permit/building-access assumptions and a line-by-line exclusions response. That should show whether the AED 532,000 difference is really price, scope or risk transfer.
 