Renovation budget for 135 m² Nairobi multifamily — handling contractor gaps

nia.voss

Homeowner
Established
KES 26,070,000 is the working budget, but the gap between two contractor prices makes that total difficult to trust. The project is a 135 m² small multifamily in Nairobi, with work planned to kitchens, bathrooms, floors, decoration, electrical systems and selected energy improvements. An extension is not part of the proposal.

Before choosing a bid, I want both contractors to price the same line items and identify every assumption, provisional allowance and omission. Which checks would best uncover inaccessible plumbing, moisture damage and the true electrical scope? I’d also appreciate views on contingency and sequencing, particularly where opening up, permit timing or long lead times could delay work that is difficult to reverse.
 
At this stage I’d provisionally carry around 15%, but only after putting both bids into the same line-by-line format. Ask each contractor to identify exclusions, provisional sums, assumed quantities, waste removal, protection of occupied areas, testing, permits and who pays for making good after electrical or plumbing access. A low total can simply mean more items have been left outside the price.
 
Also, are the units expected to remain occupied during the work, and are there reliable drawings showing the service routes? Those two answers could change the programme substantially. I would ask for separate prices for opening up, repair work and reinstatement rather than letting all three disappear into broad bathroom or electrical allowances.
 
I’m not convinced a single 15% contingency solves the problem while the scope is still this loose. Moisture can be cosmetic, failed waterproofing or a plumbing leak, and each leads to a different job. Some targeted opening-up around wet areas and likely pipe routes may be worth doing before choosing between bids. The electrical “checks” also need a defined outcome: inspection only, testing, minor corrections, or replacement where defects are found.
 
Sequencing deserves its own contractor meeting. Agree what must be exposed first, when decisions are required, and which rooms can proceed without waiting for hidden-condition work elsewhere. Request a simple programme showing inspections, permit-dependent activities and material order dates. Then ask both contractors what happens to time and cost if specified items arrive late—substitution should not be decided informally after demolition.
 
This helps. I’ll stop comparing the two headline totals and send both contractors the same breakdown request: access and opening-up, testing, remedial work, reinstatement, exclusions, permit responsibility, lead times and programme assumptions. I’ll also separate known-scope contingency from a reserve for concealed moisture, plumbing and electrical conditions. If the revised bids still differ sharply, I’ll trace the variance by work package before selecting anyone.
 