Manchester villa renovation: is £397,200 enough, and what should I investigate first?

bakesAndView

Developer
Established
If remedial electrical work or inaccessible plumbing is discovered after the finishes are ordered, the £397,200 budget could be undermined by both rework and delay. This is a preliminary allowance for renovating a 1,510 sq ft Manchester villa, covering the kitchen, bathrooms, floors, decoration, electrical investigation and moderate energy improvements, without an extension.

Before debating finishes, I want to test the assumptions behind the scope. Which surveys would best identify moisture, services and other concealed problems, and how should tenderers distinguish inspections from actual repairs? I would also like to know what exclusions, provisional sums and material lead times should be pinned down before setting the contingency.
 
The total is substantial for the stated scope, but it is difficult to judge without seeing what sits inside it. I’d ask every tenderer to separate labour, materials, provisional sums and exclusions. Also pin down whether “electrical checks” means inspection only or includes an allowance for remedial work. Vague wording there can hide a large gap.
 
How old is the villa, and has it been empty or recently occupied? Those details affect what I’d investigate first. I’d want moisture readings and the causes traced, not just a note saying damp is present. Plumbing access matters too: lifting floors after new finishes go down is exactly the sequencing problem you’re trying to avoid.
 
I wouldn’t choose a contingency percentage until the £397,200 has been split between fixed prices and unknowns. A single percentage can create false comfort if the kitchen is fully specified but concealed plumbing, wiring and moisture are not. Open up a few carefully chosen areas before final pricing, where practical, and record who pays for making good.
 
A caveat: opening up areas early is useful, but it can become its own uncontrolled mini-project. Start with the building survey and targeted follow-up questions, then agree specific inspection points with the contractor. I’d also ask whether any apparently non-structural work could affect walls, ventilation or energy measures and therefore require extra design input or approvals in Manchester.
 
The programme deserves as much attention as the price. Ask for the order of electrical and plumbing work, plastering, flooring, kitchen installation and decorating. Then request dates by which long-lead materials must be selected. If permit or approval timing is relevant to any element, it should appear in the programme rather than being treated as an afterthought.
 
Also compare exclusions line by line, not just headline totals. Typical ambiguities in this scope are removal of old finishes, disposal, access equipment, temporary protection, testing after installation and repairs to surfaces disturbed by services. I’d ask each contractor to price the same written schedule; otherwise one apparently cheaper tender may simply omit more.
 
My practical next step would be a risk register with three columns: unknown condition, how it will be investigated, and the allowance held if it cannot be resolved before contract. Put wiring, concealed pipework, moisture, substrate condition under flooring, material lead times and approval timing on it. That should make the contingency discussion far more meaningful than choosing a round percentage now.
 