How much contingency for a £126,400 Manchester duplex renovation?

wise_book

Property investor
Established
I’m 58 days into assessing a renovation of a 2,530 sq ft duplex in Manchester. My preliminary budget is £126,400 for the kitchen, bathrooms, flooring, paint, electrical checks and moderate energy upgrades. No structural extension is planned.

What contingency would people carry, and which survey or contractor questions would expose the biggest unknowns? I’m particularly concerned about sequencing, plumbing access, moisture and vague exclusions rather than finishes. I’d rather simplify the design now than run out of cash halfway through.
 
I’d carry 15–20% until the electrical, plumbing and moisture questions are better defined. Ask each contractor to state what is excluded, who opens and repairs walls or floors, whether waste removal is included, and what happens if existing services cannot support the proposed layout. A low headline quote with broad exclusions won’t help your cash-flow concern.
 
Is the duplex one dwelling over two levels, or two separate units? That changes how awkward access and sequencing may be. Also, are you moving kitchens or bathrooms? Keeping wet areas in place is very different from rerouting plumbing through finished floors.
 
I wouldn’t automatically reserve 20% across the whole £126,400. Some packages can be fixed once drawings and products are settled. Keep a larger allowance against opening-up work and existing services, but push flooring, decorating and known fixtures toward firm prices. Otherwise contingency becomes a substitute for defining the scope.
 
The electrical “checks” wording needs tightening. Does the budget cover inspection only, identified remedial work, a new consumer unit if required, or extensive rewiring? Ask what assumptions were made about access and making good. The same applies to plumbing: tracing routes before ordering the kitchen could prevent an expensive redesign.
 
Moisture deserves attention before paint, flooring or fitted cabinetry. Ask the surveyor to distinguish the likely cause rather than just recording damp readings, and have the contractor explain what must dry before finishes begin. I’d also request a room-by-room programme showing dependencies, not merely a start and completion date.
 
One more point on the programme: separate decisions from deliveries. Long-lead materials should be selected early, but don’t order items tied to unverified dimensions until opening-up is complete. The contractor should identify which measurements are safe now, which depend on demolition, and whether storage or delayed delivery creates extra cost.
 
Even without an extension, confirm whether any walls, chimney elements, floors or roof areas are being altered for the new layout or energy work. “No extension” doesn’t necessarily mean “no structural work.” Any required approvals or building-control steps should also appear in the sequence, with responsibility for arranging them made clear.
 
Do not let the £126,400 become the spending target. For this duplex, first divide it into fully specified work, provisional sums and items that no bidder has accepted responsibility for.

I would keep the contingency separate rather than allowing it to disappear into finish upgrades. Give every bidder the same written scope and ask what they intend to inspect or open up during the first two weeks. If plumbing access and hidden conditions can be checked early, retain the present design until those findings are known; if they cannot, simplify the scheme now and protect a larger reserve. That comparison should expose whether a cheaper quote reflects efficiency or merely more exclusions.
 