Denver studio renovation: how much contingency for hidden conditions?

compareTheRidge

Property investor
Established
I want the two Denver bids to be genuinely comparable, but their different assumptions make that difficult. The working budget is $314,800 for a 1,130 sq ft studio, covering the kitchen, bathrooms, floors, decoration, electrical investigation and some energy improvements. An extension is not intended.

Before choosing finishes, I need to separate easy-to-change allowances from risks that could force major work once surfaces are opened. What should each contractor disclose about exclusions, plumbing access, damp, structural findings, permits and long-lead materials? I would also be interested in how others set a contingency after those unknowns have been investigated.
 
I’d ask both contractors to reprice against one written scope and identify every exclusion and allowance. “Electrical checks” is especially vague: does it cover investigation only, minor corrections, or opening and repairing finishes if problems are found? Do the same for plumbing access and moisture damage.

For an older or poorly documented property, I’d be more comfortable around 15–20% contingency than a token amount, but first confirm the building age, previous renovation records and whether walls or floors will be opened.
 
I wouldn’t choose a contingency percentage until the two bids are normalized. One contractor may have included permits, protection, debris removal, patching and longer-lead materials while the other has not; adding 20% to an incomplete quote still leaves an incomplete budget.

Have each contractor provide a sequence, assumptions, allowances and responsibility list. Then arrange targeted investigation of likely plumbing routes, damp areas and the electrical panel before work starts. Also ask which selections must be fixed early so material lead times do not disrupt the schedule.
 