Could use some advice: renovation budget for a 1,510 sq ft warehouse in Edinburgh (2 bed)

UmaLowe

Developer
Established
I have priced the obvious rooms and finishes, but the work behind them is still unclear. The provisional figure is £131,600 for converting a 1,510 sq ft Edinburgh warehouse to a two-bedroom layout, with no extension intended.

Before setting the contingency, I need to know whether the existing structure can accept the layout, where water and drainage can run, and what the electrical allowance actually includes. Moisture and the consequences of opening floors or linings are further unknowns.

Which survey investigations would reduce those uncertainties most? I would also appreciate suggestions for questions that force contractors to identify access work, structural assumptions, making good and exclusions rather than leaving them buried in a general reserve.
 
At a preliminary stage I would allow roughly 15%, potentially nearer 20% until there has been some opening-up. “Electrical checks” is too vague for budgeting: ask whether the price assumes testing only, partial replacement or wider rewiring. I would also establish where drainage and water routes can actually run before fixing the kitchen and bathroom layouts.
 
Does the £131,600 include VAT, professional fees, permissions and any temporary works? Without knowing that, a contingency percentage may give false reassurance. Ask every contractor for a written list of exclusions and assumptions, especially making good after service installation, waste removal, access equipment, drying time and work discovered once floors or wall linings are opened.
 
I slightly disagree with simply adding 20% to the whole figure. Separate the uncertain work from items that can be firmly priced. Kitchens and visible finishes can be specified; concealed moisture, floor condition and service routes cannot. Carry a reserve for the latter and use provisional allowances where necessary. Also, no extension does not necessarily mean no structural cost if the existing roof, walls or floor need repair.
 
The sequence matters more than squeezing each trade's quote. I would go: targeted survey and agreed opening-up, settle the layout, resolve moisture and structural findings, confirm plumbing and electrical routes, then order long-lead materials and start finishes. Ask the contractor for a programme showing permit dependencies, ordering dates and who is responsible if an early assumption proves wrong.
 
Moisture would be my go/no-go item before committing heavily to flooring or fitted joinery. Ask the surveyor to distinguish the likely cause rather than just report readings, and to examine the roof, rainwater disposal, walls, floor and ventilation together.

For tender comparison, issue the same scope to everyone and request separate figures for electrical work, plumbing access, repairs and making good. Keep the contingency outside the main contract sum, with discoveries photographed, priced and approved before the reserve is used.
 