I am torn between adding one broad contingency and setting aside separate allowances for each unresolved trade. This is a 60 m² Delhi warehouse priced at ₹109,800,000, with an early works budget of ₹13,690,000. The plan includes fitting out cooking and washroom areas, renewing surfaces and decoration, checking the electrics and making modest efficiency improvements; there is no proposed extension.
The finish choices are fairly controllable, but hidden services and the order of work are not. For example, inaccessible waste pipes could force floors to be opened after another trade has started. What should the surveyor establish about damp, movement, drainage routes and the electrical installation, and what should the contractor state about exclusions, assumed quantities, approvals and delivery times? If those checks resolve the risks, I would use a general reserve; if they do not, does it make more sense to keep named allowances outside the base quote?
The finish choices are fairly controllable, but hidden services and the order of work are not. For example, inaccessible waste pipes could force floors to be opened after another trade has started. What should the surveyor establish about damp, movement, drainage routes and the electrical installation, and what should the contractor state about exclusions, assumed quantities, approvals and delivery times? If those checks resolve the risks, I would use a general reserve; if they do not, does it make more sense to keep named allowances outside the base quote?