Contingency for an £81,860 Birmingham multifamily renovation

DirectCairn

Homeowner
Established
I would like to keep this Birmingham renovation close to the preliminary £81,860 budget, but the unknowns behind the walls may make that unrealistic. It is an older 1,560 sq ft small multifamily, with work planned to kitchens and bathrooms as well as floors, decoration, electrical checks and energy improvements. There is no extension in the scope.

A large contingency is tempting, although it will not solve poor sequencing or an incomplete quotation. Plumbing access is my main concern because opening finished areas twice would be expensive and disruptive. I also need to understand whether approvals or permit timing could delay ordering and leave contractors waiting.

Before choosing a percentage, what inspections would help define the electrical, damp and pipework risks? I would also ask contractors to identify exclusions, provisional amounts, lead times and the rates used when hidden work is discovered.
 
At this stage I’d carry roughly 15–20%, but keep that separate from provisional sums already included in the £81,860. Ask each contractor to state what happens if wiring, pipework or damp damage is found after strip-out, including labour rates and who prices the remedial work. I’d also want targeted electrical, moisture and drainage information before agreeing a fixed programme.
 
I’m not sure a contingency percentage is the first issue. Does the figure include VAT, professional fees, waste removal and making good after electrical or plumbing access? Those omissions could matter more than choosing between 15% and 20%.

Is the building vacant, or will leases and resident access restrict when kitchens, bathrooms or services can be taken out? Sequencing an occupied multifamily property is a different exercise. I’d also clarify whether any proposed energy work needs approval before ordering materials.
 
The occupancy point is important. I’d split the plan into investigation, strip-out, services, making good and finishes rather than accept one broad programme. Then ask for an exclusions schedule against each phase. Hold off ordering kitchens and flooring until dimensions and moisture conditions are confirmed, while identifying long-lead items early so the contingency is not consumed by avoidable resequencing.
 