I’m testing a preliminary budget of £54,190 for renovating a 1,450 sq ft retail unit in Manchester. It covers a kitchen, bathrooms, flooring, paint, electrical checks and moderate energy upgrades. There’s no structural extension planned.
Would you treat that figure as workable before contingency, and how much contingency would you hold? I’m mainly worried about sequencing and hidden conditions rather than finish choices. Cosmetic work can be delayed, but electrical or water problems cannot. Which survey and contractor questions would reduce the biggest unknowns?
Would you treat that figure as workable before contingency, and how much contingency would you hold? I’m mainly worried about sequencing and hidden conditions rather than finish choices. Cosmetic work can be delayed, but electrical or water problems cannot. Which survey and contractor questions would reduce the biggest unknowns?