Contingency and sequencing for a £54,190 Manchester retail refit

bakesAndView

Developer
Established
I’m testing a preliminary budget of £54,190 for renovating a 1,450 sq ft retail unit in Manchester. It covers a kitchen, bathrooms, flooring, paint, electrical checks and moderate energy upgrades. There’s no structural extension planned.

Would you treat that figure as workable before contingency, and how much contingency would you hold? I’m mainly worried about sequencing and hidden conditions rather than finish choices. Cosmetic work can be delayed, but electrical or water problems cannot. Which survey and contractor questions would reduce the biggest unknowns?
 
I’d initially keep around 15% outside the £54,190 rather than quietly spreading it across the trade allowances. The key electrical question is whether the price includes only inspection and testing or also remedial work found afterwards. Likewise, ask whether plumbing prices assume existing routes can be reused and what happens if floors or walls must be opened for access.
 
What is known about the previous use and how much of the unit is currently accessible? A kitchen can change the picture if extraction, drainage or additional electrical demand is involved. I’d want the contractor to mark proposed service routes before agreeing a programme. Also clarify the condition of the distribution equipment, incoming water supply and drainage rather than treating them as generic line items.
 
I’m less convinced that choosing a contingency percentage solves this yet. “Moderate energy upgrades” is too open-ended, and no extension does not rule out remedial structural work uncovered during strip-out. Request a written list of assumptions, exclusions and provisional amounts from every contractor. If they exclude making good after electrical and plumbing access, the apparent saving can disappear quickly.
 
One more concern is moisture. Before flooring or decorating, inspect the roof edges, rear walls, thresholds and areas around existing water fittings. Ask whether any staining or damp readings need investigation and whether drying time is allowed in the schedule. Fresh finishes laid too early can turn a manageable water issue into repeated work.
 
Fifteen per cent may be reasonable once access and scope are clear, but I wouldn’t assume it is enough while services remain concealed. I’d sequence it as investigations and any required permissions first, then selective strip-out, electrical and plumbing work, drying or repairs, and only then flooring, kitchen installation and paint. Confirm approval timing and material lead times before fixing the start date. Avoid ordering fitted items until final site dimensions are verified.
 
Have all bidders price the same scope and separately identify exclusions, remedial rates and lead times. Then divide the money into essential works, contingency and deferrable cosmetics. That makes the decision easier: if opening-up reveals trouble, paint or part of the flooring can move to a later phase without consuming funds reserved for safe electrics, leaks or drainage access.
 