Contingency and hidden-condition checks for a 200 m² Bengaluru warehouse renovation

runsAndEmber

Homeowner
Established
I can either set a generous general reserve now or postpone the finishes until the building systems have been opened up. Neither option feels comfortable: the first could hide a weak scope, while the second makes the programme and final cost uncertain.

The working budget is ₹24,700,000 for a 200 m² Bengaluru warehouse, including a new kitchen and bathrooms, surface work, electrical inspection and some efficiency improvements. There is no proposed extension. Before agreeing the scope, what should be checked around permit timing, moisture, electrical capacity and access to plumbing? I would especially like to know which findings should trigger separate priced allowances rather than being left inside one contingency.
 
For context, that works out to ₹123,500 per m², but I’m wary of treating the rate as meaningful when the electrical and plumbing scope is still uncertain. I’d rather reserve money for those systems than approve all flooring and painting at the outset.
 
I would not settle on one contingency percentage yet. First ask for separate allowances for electrical correction, plumbing access and moisture repairs, rather than burying all three in a general figure. Also clarify whether opening walls or floors, disposal, temporary protection and making good are included. Those exclusions can turn a seemingly complete quotation into only the visible portion of the work.
 
What will the warehouse be used for after renovation? A basic staff kitchen and bathrooms create a very different services question from more intensive use. I’d also want the survey to trace drain routes and water entry, not merely note that fixtures and damp patches exist. If plumbing requires cutting the slab, the order of flooring, bathrooms and painting changes immediately.
 
I partly disagree with postponing all finish decisions. You can postpone colours and decorative items, but some finish choices affect floor build-up, waterproofing details and service positions. Decide those interfaces early, while delaying the actual cosmetic installation.

On moisture, ask whether staining is active or historic and have the roof, drainage points, wall junctions and slab edges examined. Otherwise fresh paint may only conceal the symptom.
 
Has the electrical check been defined? “Check” could mean anything from a visual inspection to testing circuits and assessing whether the existing supply suits the intended use. Ask the contractor to state what is being tested, what corrective work is included, and what would be priced separately after opening up.
 
I’d also request a sequence-linked quotation: investigations and opening-up first, urgent electrical/water work second, then bathrooms and kitchen, followed by flooring and paint. Attach payment points to completed sections rather than treating the renovation as one undivided package. Before ordering, ask which materials have long lead times and whether substitutions would alter dimensions or service locations.
 
Permit timing belongs on the programme even without an extension, but the relevant approvals depend on the existing building and intended use, so confirm locally rather than assuming none are needed. My practical next step would be a short paid investigation phase, followed by a revised scope and contingency based on what is exposed. Keep a separate reserve controlled by the owner, and require written approval before it is used for contractor exclusions or hidden conditions.
 