Contingency and exclusions on a €302,300 Paris apartment renovation

woodworksAndRoute

Property investor
Established
I can either carry a large contingency now or spend more time removing unknowns before fixing the budget; at this stage, the second approach feels more useful. After 54 days spent gathering and reconciling quotations, I’m working with a preliminary figure of €302,300 for a 165 m² Paris apartment.

The planned renovation includes new kitchen and bathroom work, replacement finishes, electrical investigation and measured energy improvements. There is no extension in the plan, although I still need confirmation that opening floors or walls will not reveal structural work. Contractors have treated access, protection, waste, making good and hidden plumbing conditions differently, which makes their totals difficult to compare.

What contingency would you retain until those exclusions are resolved? I’m most concerned about moisture around wet areas, the extent of electrical remedial work and whether material lead times will disrupt the sequence. Would you ask for an intrusive survey first, or require every bidder to complete the same exclusions and assumptions schedule before revising the budget?
 
I would provisionally carry 15–20% until the exclusions are reconciled, then reduce it only when the intrusive unknowns are understood. Ask each contractor to price the same written scope and state who covers opening and making good walls, waste removal, temporary protection, access constraints and work revealed after demolition.

Also clarify whether “electrical checks” means inspection only or includes bringing circuits into acceptable condition. Have plumbing routes, shutoffs and signs of moisture examined before locking the kitchen and bathroom sequence.
 
I wouldn’t reduce the contingency merely because the quotes become easier to compare. A consistent scope can still conceal conditions behind floors and wet-area finishes. Are long-lead materials already selected, and does the 54-day period include any building approvals or permit timing? I’d separate contingency from allowances for undecided items, then require a programme showing demolition, investigations, electrical and plumbing work, drying time, finishes and delivery dates.
 