I can either carry a large contingency now or spend more time removing unknowns before fixing the budget; at this stage, the second approach feels more useful. After 54 days spent gathering and reconciling quotations, I’m working with a preliminary figure of €302,300 for a 165 m² Paris apartment.
The planned renovation includes new kitchen and bathroom work, replacement finishes, electrical investigation and measured energy improvements. There is no extension in the plan, although I still need confirmation that opening floors or walls will not reveal structural work. Contractors have treated access, protection, waste, making good and hidden plumbing conditions differently, which makes their totals difficult to compare.
What contingency would you retain until those exclusions are resolved? I’m most concerned about moisture around wet areas, the extent of electrical remedial work and whether material lead times will disrupt the sequence. Would you ask for an intrusive survey first, or require every bidder to complete the same exclusions and assumptions schedule before revising the budget?
The planned renovation includes new kitchen and bathroom work, replacement finishes, electrical investigation and measured energy improvements. There is no extension in the plan, although I still need confirmation that opening floors or walls will not reveal structural work. Contractors have treated access, protection, waste, making good and hidden plumbing conditions differently, which makes their totals difficult to compare.
What contingency would you retain until those exclusions are resolved? I’m most concerned about moisture around wet areas, the extent of electrical remedial work and whether material lead times will disrupt the sequence. Would you ask for an intrusive survey first, or require every bidder to complete the same exclusions and assumptions schedule before revising the budget?