Before I reply: renovation budget for a 70 m² Warsaw warehouse

handy_page

Property investor
Established
If the electrical or moisture scope is wrong, the budget could be committed before the most disruptive work is understood. I am reviewing contractor responses for a 70 m² Warsaw warehouse against a preliminary total of PLN 544,200.

The planned work covers a kitchen, bathrooms, floors, painting, electrical inspection and some energy improvements. There is no proposed extension. Finishes can be adjusted later; concealed services, access and the order of work cannot be corrected so easily once installation starts.

Each contractor has excluded different items, and their material lead times are not presented consistently. What contingency would be sensible before those gaps are resolved, and which questions would force bidders to distinguish testing from electrical repairs, materials from labour, and opening-up work from reinstatement?
 
For this type of unknown, I’d initially reserve 15%, with room to reach 20% if plumbing access, moisture or the electrical condition remains unclear. On PLN 544,200, that is PLN 81,630 to PLN 108,840.

Before accepting anything, send all bidders the same scope table. Ask whether “electrical checks” includes only testing or remedial work, who pays for opening and reinstating floors or walls, and what happens if moisture is found. No extension does not necessarily mean no structural repairs.
 
I wouldn’t settle on 15–20% until you know whether the quotes already contain allowances for risk; otherwise you may count the same uncertainty twice. Are design costs, permit-related work, VAT and long-lead materials included? Also, does the warehouse already have functioning water and drainage where the kitchen and bathrooms are planned?

I’d ask each contractor to reissue the price with exclusions, provisional items, lead times and sequencing shown separately. That will reveal whether the apparent price differences are real.
 