€395,500 renovation budget for 65 m² student housing in Utrecht

yard.steady

Homeowner
Established
€395,500 for 65 m² already leaves little room for a vaguely defined scope. The Utrecht student-housing plan has no extension, but it does include new finishes, kitchen and bathroom work, electrical inspection and some energy improvements.

My concern is that “checks” may mean minor corrections in one tender and substantial replacement in another. Plumbing access, moisture behind finishes and contractor exclusions could produce the same problem. Before choosing a contingency, which surveys would you commission, what should every contractor price explicitly, and how would you account for permit timing or work discovered after opening walls?
 
At that budget level, I would not start by adding one blanket contingency. First split the estimate into defined work, provisional allowances and genuinely unknown work. Ask every contractor to list exclusions explicitly, including opening and making good, waste removal, access constraints and work revealed after demolition. Only then decide whether a contingency around 10–15% is enough; unresolved plumbing or electrical replacement could justify more.
 
A few missing facts could change the answer considerably. Is the property occupied during the work, and are any pipes, meters or electrical components shared with the wider building? Also, does “electrical checks” mean inspection and minor repairs, or is replacement already allowed for? The same applies to the bathrooms: moving drainage is a very different job from replacing fittings in their current positions.
 
Also, no extension does not necessarily mean no structural uncertainty. Before tendering, identify any walls to be opened, heavy fixtures to be relocated and floors affected by new service routes. I’d ask for a moisture inspection around wet rooms and external walls, plus a clear drawing of proposed plumbing access. Otherwise contractors may price different assumptions and their totals will not be comparable.
 
I agree about clarifying assumptions, but I would be cautious about opening everything before appointing a contractor. Investigations can themselves require access, reinstatement and coordination. A practical alternative is a separately priced enabling phase: limited opening-up, moisture tracing and service verification, followed by a stop/go budget update. Make sure the main quotation states the rates or method for dealing with discoveries, rather than leaving every hidden condition as an undefined extra.
 
I’d turn this into a sequence before debating finishes: confirm whether permissions are needed, map existing electrical and plumbing routes, investigate moisture, freeze the room layouts, then obtain like-for-like contractor breakdowns. Ask each bidder which materials have long lead times and what must be ordered before demolition. Keep contingency outside the contractor’s base sum, with approval required before it is used. That should expose whether €395,500 reflects real complexity or simply broad allowances.
 