For the next round, issue a simple room-by-room scope plus an exclusions sheet. Have bidders separately price demolition, disposal, temporary protection, electrical work, plumbing, moisture treatment, making good and finishes. Add columns for allowance, fixed price and excluded. That makes gaps...