I would initially reserve 15–20%, then reduce it only after opening up the main unknowns. Ask contractors to list exclusions in writing: rewiring beyond visible defects, concealed plumbing replacement, waterproofing repairs, floor levelling, debris removal, access restrictions and protection of...