I would phrase the offer roughly as: price based on current condition and limited evidence from comparable completed transactions; financing evidence available; completion timing flexible; subject to satisfactory technical and financing review. Neutral, factual, and no commentary about the...
Before the quotations are locked, there is a choice between funding uncertainty and investigating it. A larger reserve helps with the bill, but it does not tell you whether opening the wall will delay plumbing, electrical work or the permit programme.
Can the wall, damp-risk areas and...
I’m not convinced that simply adding 20% makes this safe. For 165 m², the larger risk may be an under-scoped base budget rather than isolated surprises. Get contractors to price the same written schedule, identify provisional items, and explain what happens if testing reveals wiring or moisture...